BuildQS variation schedules: group changes and omissions

Keep related additions and omissions together in a BuildQS variation schedule. Learn how to group tasks, omit original work and check a replacement-work example.

Luke Sanders

Luke Sanders

IT Developer

BuildQS variation schedules guide cover over a stock photograph of a person reviewing a technical drawing on screen
Table of contents

A specification change can involve more than one extra item. The original work may need to come out, replacement work needs pricing, and a few associated tasks may belong to the same instruction. A construction variation schedule gives those connected changes a place together.

In BuildQS, you can record a single variation or create a schedule heading for related tasks. Where variation schedules are available in your account, that heading can also hold linked omissions from the original Master Valuation Schedule. The original work stays recorded, with the adjustment shown separately.

This walkthrough covers choosing the right structure, adding tasks, omitting original work and checking a worked replacement example. It focuses on the project records, not the contractual process for agreeing a variation. All example descriptions, references and figures below are fictional.

1. Choose a single variation or a variation schedule

Choose Single variation when one priced line describes the change. Choose Variation schedule when you need a named heading with several related lines beneath it. Both choices are in the Add variation dialog, so you can decide how to record the change before entering it.

A single variation suits a self-contained item: an additional access panel, for example, with its own quantity and rate. If there is only one line to explain, a separate group may add little.

A schedule is useful when one change has several parts. A revised lighting specification could include replacement fittings, additional testing and the omission of fittings no longer required. Those are different valuation lines, but they explain the same change. A heading such as “Revised lighting specification” gives them a shared description and reference.

The distinction is about structure. Creating the heading doesn't price the replacement work or decide which original items should be omitted. You add the priced tasks and select any omissions separately.

You can relate the schedule to an original phase, or choose Whole Project for a heading without a linked original phase. Pick the relationship that reflects the work. A change relating to the lighting phase belongs there; one spanning several original phases may need a whole-project heading.

That choice also matters when you omit work. A phase-linked heading's original-work picker is restricted to that phase and its original tasks. A whole-project heading can select eligible original work across the project.

If you need background on the commercial process rather than the software structure, read our guide to variations in UK construction contracts.

Start in the project's Master Valuation Schedule. Open Add, choose Add variation, then select Variation schedule. Enter a clear description and review the variation reference. Select a related original phase, or leave the relationship at Whole Project, then save the heading.

This creates the heading only. You don't need to invent a nominal task, quantity or rate to make the group exist.

Next, use Add task on that heading to enter the priced lines. Each task uses the heading's reference, so the group keeps a common identity while its descriptions, quantities and rates explain the individual elements.

For a revised lighting specification, you might add:

  • Replacement fittings, with the number of fittings and their rate.
  • Additional testing, as a separate priced item.

Keep descriptions specific enough to distinguish the tasks. “Replacement fittings to revised specification” and “Additional testing” tell the reader more than two lines both called “Extra works”. Record an omission through the Omit action, described below, so it stays linked to the original source.

Choose the view that suits the review

The Master Valuation Schedule offers two ways to look at the saved work:

  • By phase shows original work alongside related variations, grouped by phase.
  • By schedule shows the work schedule followed by the variation schedule.

Use By phase when you want to review a change beside the original package. By schedule is useful when you want to read the changes separately from the original work.

Switching views doesn't create another variation or add its value again. It changes how the same records are displayed. A heading created without a linked original phase also stays standalone; recording an omission inside it doesn't silently attach it to the source phase.

If you are setting up the original work first, our Master Valuation Schedule guide explains the wider starting point.

3. Omit original tasks or phases when the scope changes

Use Omit… on the variation heading to select original work that is no longer required. The adjustment is recorded inside that heading. It doesn't delete the original task or phase, and this omission operation doesn't rewrite existing submitted applications.

The picker identifies the original phase and its tasks. Check both before saving, especially if several phases contain similar descriptions. “Light fittings” in one area isn't necessarily the same source as “Light fittings” elsewhere.

For a new omission, the choices are:

  • A task: omit its whole remaining original quantity.
  • A phase: omit the whole remaining original scope within that phase.

The current dialog isn't a free-entry percentage or partial-quantity calculator. If a task has already been partly omitted in an earlier record, a new whole-task omission uses the remaining available quantity, not the original quantity again.

Check the source and adjustment before saving

After choosing the original work, review the displayed source, destination heading and net adjustment. Add the variation date and, where useful, a reason explaining why the work is coming out.

The omission reverses the relevant recorded source value. It isn't a new price for replacement work. Replacement tasks belong on their own lines, even when they sit beneath the same heading.

Already omitted scope, or scope reserved by another pending omission, isn't available for a second deduction. Zero-valued original work may also be unavailable. If an option is disabled, check the source's existing adjustments rather than creating another deduction by hand.

For a whole-phase omission, later additions recorded as variations are not automatically swept into the original-work deduction. Review those separately. Removing the original phase's scope doesn't mean every later change associated with that phase has also been removed.

Saving is not the same as approval

Saving creates pending variation tasks. Review them before using the heading's approval action. Fully omitted original work is marked as omitted after approval, with a reference back to the adjustment; a pending save alone doesn't make the original work appear fully omitted.

Choose an omission date after the latest submitted application's date. The date check prevents a new adjustment being backdated into an already issued application through this workflow. Approval in BuildQS also isn't proof that the payer has contractually agreed the change, certified it or paid it.

For the information to check when preparing the later application, see our construction payment application checklist.

4. Worked example: replace original work within one schedule

Consider a fictional project with an original scope value of £120,000. That includes a lighting task for 20 standard fittings at £120 each, giving an original line value of £2,400.

The specification changes before this work has been applied for. All 20 original fittings are being replaced, and additional testing is required. Assume no previous omissions, discounts, other variations or earlier applications. The figures below are scope values before VAT, CIS, retention or other payment adjustments.

Create the group

Create a Variation schedule called Revised lighting specification, using an illustrative reference such as VO-003, and relate it to the original lighting phase. The reference is simply an example; review the reference offered in your own project.

Record the original-work omission

Use Omit on that heading and select the original fittings task. Its whole remaining quantity is 20, so the linked omission is:

  • Original recorded value: 20 × £120 = £2,400.
  • Omission adjustment: −£2,400.

The original £2,400 task remains recorded. The negative adjustment explains why that scope is being taken out; it doesn't overwrite the original rate with the replacement rate.

Add the replacement work

Use Add task on the same heading for the new items:

  • Replacement fittings: 20 × £155 = £3,100.
  • Additional testing: 1 × £400 = £400.

The additions total £3,500. Alongside the omission, the change is:

−£2,400 + £3,100 + £400 = +£1,100.

That is the difference between the original work removed and the replacement package added. The £3,500 additions aren't, by themselves, the net increase in scope.

Read the result without confusing it with payment

If these are the only changes and all are agreed, the illustrative revised scope total is £121,100: £120,000 plus £1,100. You can explain the movement using the original line and the linked changes under one heading.

This is not a claim that a £1,100 payment is now due. Application timing, work completed, approval, certification and deductions still need separate consideration. Check pending and approved statuses before using any figure in an application.

The same structure works when a phase is removed rather than a single task: select the eligible original phase in the omission picker, then keep any replacement additions on their own lines. The amount depends on that phase's remaining original scope, not on the total of every later variation linked to it.

Frequently asked questions

Can I group several tasks under one variation reference?

Yes. Create a Variation schedule heading, then use Add task on that heading for its priced lines. Those tasks use the heading's reference. A single variation is the alternative when one priced line is enough to describe the change.

Can I omit a whole phase instead of selecting every task?

Yes, where that original phase is an eligible source for the heading. The omission covers the phase's whole remaining original scope. Later variation additions are separate, and previously omitted or pending-reserved scope isn't deducted again.

Can I enter a partial quantity in the omission dialog?

Not in the current new-omission workflow. It uses the whole remaining task quantity or phase scope. Earlier partial adjustments can affect what remains available, but their existence doesn't mean the new dialog offers editable partial quantities.

Does omitting work delete it from the original schedule?

No. The original record remains, with a linked variation adjustment recorded separately. Saving leaves that adjustment pending. Once a full omission is approved, the original work is shown as omitted with a reference identifying the change; existing submitted applications aren't rewritten by the omission operation.

Consider BuildQS for your project workflow

Review the plans for your team. If you want to walk through variation schedules and original-work omissions first, use the demo link below to discuss availability and fit.

See pricingBook a Demo

Prefer to walk through your workflow live first? Book a Demo

Sources

  • BuildQS variation-schedule creation, grouping and original-work omission workflow, implementation and focused checks reviewed on 17 November 2026. The steps describe that workflow where available; account access and release availability should be confirmed before use.
  • Variations in UK construction contracts, for broader commercial context.
  • Master Valuation Schedule guide, for original project scope and valuation structure.

The worked example is fictional and illustrates scope arithmetic only. It is not customer evidence, a statement of payment entitlement or legal advice.